September 2024 Construction Update

Construction Update September 17, 2024

DOWNTOWN WATER IMPROVEMENTS

CONSTRUCTION NOTICE UPDATE

Click HERE for printable Construction Update Notice (pdf)

The City of Wahoo Utilities continues to enhance its water infrastructure to provide reliable, high-quality service across the city. Here’s what you can expect in the next phase of construction that is replacing outdated water mains and service lines across 33 blocks of the downtown business area.

Phase 2

  • · North Linden Street & E 4th Street:  Service line construction is anticipated to be completed as early as the 2nd week of September.
  •   North Linden Street (E 5th Street and E 6th Street): Construction will continue through September.

Phase 3

  • · North Linden Street (E 7th Street to E 8th Street): Service line construction is anticipated to begin as early as the second week of September.

Important Information

  • · Temporary parking spots and sidewalk closures will occur, but there will be no street closures at any location.
  •   Access to all businesses will be maintained throughout the construction period.

Construction Map

  • · Click HERE for a construction map.

CONTACT US

For specific comments or questions during the construction process, please call City Hall at (402) 443-3222. You can also visit our website at wahoo.ne.us for updated information.

Thank you in advance for your patience and cooperation as we work to improve water service reliability and fire protection for our community.